MARAD Accelerates Texas LNG Port Approval
MARAD granted conditional approval for ST LNG's $8.2 billion deepwater port off Texas, completing review 70% faster than historical averages.

The U.S. Department of Transportation's Maritime Administration (MARAD) has granted conditional approval for ST LNG's $8.2 billion deepwater port project off Matagorda, Texas. The license review was completed nearly 3.7 years faster than the historical average.
Accelerated Review Process
The project's review time was reduced by 70%. This dramatic acceleration stemmed from a restructuring of the approval framework initiated in January, when MARAD assumed the sole lead agency role. The U.S. Coast Guard shifted to a supporting role focused on vessel operations and maritime safety.
The previous co-lead structure created duplicative administrative steps and sequential reviews. A DOT spokesperson explained that "the primary efficiency gained was fixing a structural inefficiency, rather than addressing challenges within any specific partner agency." MARAD consolidated project schedules, aligned public comment periods, and engaged cooperating agencies earlier in the process. The agency completed the Final Environmental Impact Statement in 410 days.
Project Scope and Design
The port will be constructed in four phases approximately 10 miles offshore from Matagorda. It is a major infrastructure undertaking designed to liquefy and export natural gas.
| Component | Quantity/Description |
|---|---|
| Fixed Offshore Platforms | 5 (Gas Treatment, Liquefaction, Bridge Support Trestle, LNG Transfer, Accommodation/Utilities) |
| Total Platforms | 20 |
| Floating LNG Storage Units | 4 |
| Liquefaction Systems | 4 |
| System Capacity | 2.1 million tonnes per annum (MTPA) each |
| Pipeline Infrastructure | 7.7 miles total (5.6-mile lateral, 2.1 miles interconnecting) |
| Mooring System | Dolphin system with 3 berthing and 6 mooring dolphins |
Feed gas will be supplied via the Transco pipeline from the Tres Palacios Natural Gas Storage and Trading Hub and the Williams Markham Gas Processing Plant.
Job Creation and Capacity Impact
The construction phase will support more than 2,000 jobs, with up to 855 permanent positions once operational. Upon completion, the facility is projected to expand American LNG export capacity by 7 to 9 percent. The project is expected to generate thousands of jobs in the Gulf region, strengthen supply chains, and help drive down energy prices.
Regulatory Compliance Requirements
Approval is not yet final. ST LNG must demonstrate compliance with nine specific conditions before a license is issued. The company must agree in writing not to alter its approved application and submit all compliance documentation at least 90 days prior to license issuance. Key regulatory partners, including the U.S. Coast Guard, were listed as cooperating agencies in the project's Record of Decision. Neither the U.S. Environmental Protection Agency Region 6 nor the U.S. Army Corps of Engineers filed objections.
The port's offshore location is intended to move vessel traffic away from congested onshore areas, thereby reducing collision and safety risks. Construction is scheduled to begin in 2027, with the port coming online in 2029.





